有人说为啥这么贵
这东西好像就产学合作出来的
在其他地方整个做好再搬过去一起装起来
号称可以减少施工期间的交通阻碍,也可以降低危险性(?)
他们学校之前发的新闻
https://tinyurl.com/y9ct5bwl
节录一些
The 174-foot, 950-ton section of the bridge was built adjacent to Southwest
Eight Street using Accelerated Bridge Construction (ABC) methods, which are
being advanced at FIU’s Accelerated Bridge Construction University
Transportation Center (ABC-UTC). This method of construction reduces
potential risks to workers, commuters and pedestrians and minimizes traffic
interruptions. The main span of the FIU-Sweetwater UniversityCity Bridge was
installed in a few hours with limited disruption to traffic over this weekend.
这种工法其实他们也不是第一个发明的
这边谈到这座天桥是用他们大学改进出来的桥梁加速建造工法
The FIU-Sweetwater UniversityCity Bridge is the largest pedestrian bridge
moved via Self-Propelled Modular Transportation in U.S. history.
号称目前是美国最大型的预建后移动组装的天桥